Exterior First or Interior First in a Carlsbad Repaint

Most people assume the outside should wait for the nicest weather, and that the inside can fill any gap. On a whole-house repaint in Carlsbad, CA the reverse is often true, and the notes kept on carlsbad house painting compton police gangs explain why the exterior window usually sets the schedule while the interior fills the days around it.
Weather decides the exterior window

Carlsbad has long dry stretches and a rain season that is concentrated in winter. Summer brings marine fog that can sit on a house until late morning and leave stucco damp. Exterior latex needs a dry surface and a stretch without rain or heavy dew, so the outside is booked into the clearest weeks, and the rest of the work moves to match.
Why the outside usually goes first

Exterior prep makes dust and mess. Scraping, sanding and washing send grit toward windows and doors, and a sprayer puts a fine mist on anything not masked. Doing that before the inside is painted keeps new interior paint clean, and windows get cleaned once after the exterior is done, instead of twice.
When the interior can go first
If the rain season is close, or fog is lingering on the coast around Agua Hedionda Lagoon, interior work can go first and the exterior waits for a drier week. Ceilings, walls and trim inside do not care about the weather. Interior patching, spackle and a scuff sand can be done while the outside is still drying from a wash.
Shared surfaces cross both lists
Some parts belong to both. Front and back doors need paint inside and out, and window casings have an interior face and an exterior face. Those are painted on one visit, with a semi gloss or satin enamel on both sides, so the door is closed and hung again in a day and the frame does not get a mismatched edge.
A rough order for a full job
A common sequence is exterior wash and repairs, exterior prep and primer, interior patching and ceilings, exterior topcoat in two coats, interior walls, then trim and doors on both sides and a final check. The exact order changes with the forecast, but the idea stays the same: dirty work first, finish coats last, and everything checked in daylight.